Search Your Queries Related To Trilegal
Update

Andhra Pradesh High Court on re-determination of tariff under existing PPAs

17 Mar 2022

Trilegal X Athena banner image In yellow color

Settling long-standing issues
plaguing the renewable energy
sector in Andhra Pradesh, a
Division Bench of the Andhra
Pradesh High Court has held,
amongst other directions, that
the tariff under concluded
power purchase agreements
between power generating
companies and state
distribution companies cannot
be renegotiated.

Background

In September 2018, the distribution companies in Andhra Pradesh (Discoms) filed a petition before the Andhra Pradesh Electricity Regulatory Commission (APERC) for reduction in the preferential feed-in tariff applicable to wind power projects determined under Section 62 of the Electricity Act, 2003 (Electricity Act).

Subsequently, they also filed a similar petition impacting solar developers, requesting the APERC to revise the tariff payable by the Discoms for procurement of solar power (discovered under Section 63 of the Electricity Act through competitive bid process). They contended that the tariff discovered in other states pursuant to competitive bidding was lower than the preferential tariff fixed by the APERC and also the tariff discovered through the competitive bid process.

Thereafter, various solar and wind power developers approached the High Court of Andhra Pradesh to challenge the proceedings before the APERC. A single judge of the High Court dismissed the petitions on 24 September 2019 (Common Order), with a direction to the APERC to decide the issues raised by the developers. However, it directed the Discoms to pay interim tariff (which was lower than the tariff under the PPAs) to the wind and solar power generators until the matter was adjudicated by the APERC.

The Common Order created numerous hardships for the power generators – to the extent that in few instances even the lower interim tariff was not paid by the Discoms. Lenders to these projects were forced to declare few assets as ‘non-performing’, resulting in project developers having to seek relief from the courts to restrain lenders from proceeding against these projects as ‘non-performing assets’.

Aggrieved by the Common Order, the developers filed writ appeals before the Division Bench of the High Court. Pursuant to a fairly lengthy process of over 3 years, the Division Bench has determined several longstanding issues and provided much-needed relief to the power generators. In summary, it held that: (i) the tariff under concluded PPAs cannot be re-negotiated; (ii) financial difficulty of Discoms is not a ground to permit non-performance of the PPAs or to reduce the tariff set out under the PPAs; (iii) tariff determined through competitive bidding process under Section 63 of the Electricity Act cannot be re-determined; and (iv) since the renewable energy plants operate on a ‘must-run basis’, any arbitrary curtailment of power by the state load despatch centre (without any prior notice and not based on grid security or safety reasons) is illegal.

We discuss the key issues and the decision in detail below.

Download PDF to read more

Subscribe to our Knowledge Repository

If you would like to receive content directly in your inbox from our knowledge repository, please complete this subscription form. This service is reserved for clients and eligible contacts.







    Let's connect

    Disclaimer

    Under the rules of the Bar Council of India, Trilegal is prohibited from soliciting work or advertising in any form or manner. By accessing this website, www.trilegal.com, you acknowledge that:

    • You are seeking information about Trilegal of your own accord and there has been no form of solicitation, advertisement or inducement by Trilegal or its members.
    • This website should not be construed as providing legal advice for any purpose.
    • All information, content, and materials available on this website are for general informational purposes only.
    • Any information obtained or material downloaded from this website is completely at the user’s volition, and any transmission, receipt or use of this website is not intended to, and will not, create any lawyer-client relationship.
    • Information on this website may not constitute the most up-to-date legal or other information. Trilegal is not liable for the consequences of any action taken by any person based on any material or information available on this website, or for any inaccuracy in or exclusion of any information or interpretation thereof.
    • Readers of this website or recipients of content or information available on this website should not act based on any or all such content or information, and should always seek advice of competent legal counsel licensed to practice in the appropriate jurisdiction.
    • Third party links contained on this website re-directing users to such third-party websites should neither be construed as legal reference / legal advice, nor considered as referrals to, endorsements of, or affiliations with, any such third party website operators.
    • The communication platform provided on this website should not be used for exchange of any confidential, business or politically sensitive information.
    • The contents of this website are the intellectual property of Trilegal.

    We prioritize your privacy. Before proceeding, we encourage you to read our privacy policy, which outlines the below, and terms of use to understand how we handle your data:

    • The types of information we collect and why we collect them.
    • How we use your information to provide a personalized experience.
    • The measures we take to ensure the security of your data.
    • Your rights and choices in managing your personal information.
    • How we may share information with trusted partners for specific purpose.

    For more information, please read our terms of use and our privacy policy.

    Up arrow