Search Your Queries Related To Trilegal
Update

Dispute Resolution Quarterly Milestones (January-March 2026)

21 Apr 2026

Financial Regulatory Regime Quarterly Milestones (January-March 2025)

In this update:

Supreme Court:

  • clarifies that courts can extend arbitrator’s mandate post-award to prevent delayed award from becoming infructuous
  • clarifies that substitution of arbitrator is not automatic upon termination of mandate under Section 29A of Arbitration Act
  • clarifies that ongoing settlement discussions do not bar financial creditors from initiating insolvency proceedings
  • applies ‘transnational issue estoppel’ doctrine to prevent relitigation of substantive issues at enforcement stage of foreign arbitral award

Partner: Mohit Rohatgi, Senior Associate: Ashwini Tak, Associate: Umang Bhat Nair

Key Developments

1.Supreme Court clarifies that courts can extend arbitrator’s mandate post-award to prevent delayed award from becoming infructuous

The Supreme Court held in C. Velusamy v K Indhera1 that an application under Section 29A(5) of the Arbitration and Conciliation Act, 1996 (Arbitration Act) to extend the arbitrator’s mandate is maintainable even after the statutory timeline for making the award has expired, including where the award was made after the mandate expired.

In this case, a sole arbitrator was appointed by the Madras High Court on 19 April 2022 in a dispute arising from three agreements to sell. The parties extended the arbitrator’s mandate by six months, until 20 February 2024, and arguments concluded within this extended period. The proceedings were later reopened due to settlement discussions. When discussions failed, the arbitrator delivered the award on 11 May 2024, after the mandate had expired. The award debtor sought to set aside the award, while the award creditor sought extension of the mandate. The Madras High Court refused to extend the arbitrator’s mandate since the award had already been delivered.

On appeal, the Supreme Court held that an award made after expiry of the mandate is ineffective and unenforceable unless the court extends the mandate. However, the court’s jurisdiction to entertain an application under Section 29A is not lost merely because the mandate has expired or because an award has been delivered in the interim.

The decision reinforces that Section 29A is intended to facilitate completion of arbitration proceedings rather than defeat them on a technicality, while preserving the court’s ability to impose costs, reduce fees, or attach conditions where the facts warrant. For parties to arbitration, it reduces the risk that time and costs incurred in the arbitration will be wasted solely because the award was delivered after the Section 29A deadline.

2.Supreme Court clarifies that substitution of arbitrator is not automatic upon termination of mandate under Section 29A of the Arbitration Act

In Viva Highways Ltd. v M.P. Road Development Corpn. Ltd.,2 the Supreme Court clarified that substitution of an arbitrator is not an automatic and inevitable consequence of the termination of his or her mandate under Section 29A (6) of the Arbitration Act.

The law prescribes strict timelines to complete arbitration proceedings. When these timelines expire, an arbitrator’s mandate terminates unless extended by a court. Here, the High Court of Madhya Pradesh relied on previous Supreme Court rulings, including Mohan Lal Fatehpuria v Bharat Textiles,3 to hold that once this timeline expires, the existing arbitrator’s mandate must be terminated and a substitute arbitrator appointed.

The Supreme Court set aside this interpretation and clarified the scope of Section 29A(6), holding that:

  • While courts have the power to substitute an arbitrator after the timeline expires, such substitution is discretionary and not mandatory;
  • The decision to appoint a substitute arbitrator must be based on the specific facts and circumstances of the case.

The Court emphasised that automatic substitution would lead to duplication of effort and proceedings, increased costs, and inefficiencies, particularly where substantial progress has already been made in the arbitration.

This ruling reinforces procedural flexibility in preserving efficiency in arbitral proceedings. It serves as a reminder to courts to adopt a reasoned, case-by-case approach rather than a rigid, mechanical application of timelines and provisions that could inadvertently undermine the objectives of the Arbitration Act.

3.Supreme Court clarifies that ongoing settlement discussions do not bar financial creditors from initiating insolvency proceedings

The Supreme Court, in Catalyst Trusteeship Ltd. v Ecstasy Realty Pvt. Ltd.,4 held that ongoing settlement or restructuring discussions do not preclude a financial creditor from filing an insolvency initiation application under Section 7 of the Insolvency and Bankruptcy Code, 2016 (IBC).

In this case, the borrower had defaulted on redeemable non-convertible debentures worth INR 600 crore. When the debenture trustee initiated insolvency proceedings, the borrower argued that such proceedings could not be undertaken when a restructuring plan was already being negotiated with one of the debenture holders via email. The insolvency application was dismissed by the National Company Law Tribunal (NCLT) and later by the National Company Law Appellate Tribunal (NCLAT). Both the authorities held that, as the debenture trustee and other debenture holders were aware of the ongoing negotiations, they had, by conduct, agreed to a moratorium on enforcement of defaults during the negotiation period.

The Supreme Court set aside these findings and clarified that:

  • The concept of a “pre-existing dispute” is a defence against operational debts (like unpaid vendors), and hence operational creditors are barred, under Section 9 of the IBC, from initiating insolvency proceedings during the pendency of such disputes. However, this concept could be extended to prevent financial creditors (like lenders and bondholders) from filing insolvency applications.
  • Contractual terms must be strictly enforced. The Debenture Trust Deed expressly required the written consent of all debenture holders to modify its terms. Informal negotiations with only one debenture holder could not alter or suspend the borrower’s obligations.

This decision reinforces the sanctity of contractual terms and clarifies that insolvency proceedings cannot be derailed by informal or unilateral settlement discussions. It also underscores that amendment provisions in financing documents must be complied with in both form and substance.

4.Supreme Court applies ‘transnational issue estoppel’ doctrine to prevent relitigation of substantive issues at enforcement stage of foreign arbitral award in India

The Supreme Court, in Nagaraj V. Mylandla v PI Opportunities Fund-I,5 upheld the enforcement of a Singapore-seated arbitral award, affirming the applicability of the “transnational issue estoppel” doctrine in India.

The dispute arose from an award by a Singapore-seated arbitral tribunal directing the promoters of an Indian company (i.e., the award debtor) to pay damages equivalent to the exit price for the surrender of shares held by certain investors (i.e., the award creditor). The award debtor failed in its challenge to the award before the Singapore courts. It then attempted to resist the enforcement of the award in India by contending that the surrender of shares amounted to an illegal “buy-back” under Indian law and was therefore contrary to India’s public policy.

Rejecting this contention, the Supreme Court held that issues raised and adjudicated upon by the courts at the seat of arbitration cannot be relitigated at the enforcement stage. Such reopening of issues by the parties is precluded by the doctrine of “transnational issue estoppel.”

This decision reinforces India’s pro-enforcement stance toward foreign arbitral awards and promotes certainty by ensuring that parties do not get a ‘second bite at the cherry’ to relitigate settled issues or delay the execution of awards.


[1] 2026 SCC OnLine SC 142

[2] 2026 SCC OnLine SC 195

[3] 2025 SCC OnLine SC 2754

[4] 2026 SCC OnLine SC 300

[5] Special Leave Petition (Civil) Nos. 31866-68 of 2025


If you require any further information about the material contained in this newsletter, please get in touch with your Trilegal relationship partner or send an email to alerts@trilegal.com. The contents of this newsletter are intended for informational purposes only and are not in the nature of a legal opinion. Readers are encouraged to seek legal counsel prior to acting upon any of the information provided herein.

Trending Articles

Subscribe to our Knowledge Repository

If you would like to receive content directly in your inbox from our knowledge repository, please complete this subscription form. This service is reserved for clients and eligible contacts.







    Let's connect

    Disclaimer

    Under the rules of the Bar Council of India, Trilegal is prohibited from soliciting work or advertising in any form or manner. By accessing this website, www.trilegal.com, you acknowledge that:

    • You are seeking information about Trilegal of your own accord and there has been no form of solicitation, advertisement or inducement by Trilegal or its members.
    • This website should not be construed as providing legal advice for any purpose.
    • All information, content, and materials available on this website are for general informational purposes only.
    • Any information obtained or material downloaded from this website is completely at the user’s volition, and any transmission, receipt or use of this website is not intended to, and will not, create any lawyer-client relationship.
    • Information on this website may not constitute the most up-to-date legal or other information. Trilegal is not liable for the consequences of any action taken by any person based on any material or information available on this website, or for any inaccuracy in or exclusion of any information or interpretation thereof.
    • Readers of this website or recipients of content or information available on this website should not act based on any or all such content or information, and should always seek advice of competent legal counsel licensed to practice in the appropriate jurisdiction.
    • Third party links contained on this website re-directing users to such third-party websites should neither be construed as legal reference / legal advice, nor considered as referrals to, endorsements of, or affiliations with, any such third party website operators.
    • The communication platform provided on this website should not be used for exchange of any confidential, business or politically sensitive information.
    • The contents of this website are the intellectual property of Trilegal.

    We prioritize your privacy. Before proceeding, we encourage you to read our privacy policy, which outlines the below, and terms of use to understand how we handle your data:

    • The types of information we collect and why we collect them.
    • How we use your information to provide a personalized experience.
    • The measures we take to ensure the security of your data.
    • Your rights and choices in managing your personal information.
    • How we may share information with trusted partners for specific purpose.

    For more information, please read our terms of use and our privacy policy.

    Up arrow